During which of the following process steps of sales and operations planning would resource planning be carried out?
A. Demand planning phase
B. Supply planning phase
C. Pre-sales and operations planning meeting
D. Executive sales and operations planning meeting
Answer: B
In a make-to-order environment, if cumulative production exceeds cumulative demand, which of the following outcomes will result?
A. Excess capacity will exist.
B. Inventory will increase.
C. The backlog will increase.
D. The backlog will decrease.
Answer: D
We promise that we will do our best to help you pass the APICS certification CPIM-MPR exam.Passtcert can not only achieve your dreams, but also provide you one year of free updates and after-sales service. The CPIM certification CPIM-MPR practice questions of Passtcert is 100% correct and they can help you pass APICS certification CPIM-MPR exam successfully. You can free download part of CPIM certification CPIM-MPR practice questions online as a try.
If you're still studying hard to pass the APICS CPIM-MPR exam, Passtcert help you to achieve your dream. We provide you with the best CPIM certification CPIM-MPR practice questions. It passed the test of practice, and with the best quality. It is better than CPIM certification CPIM-MPR practice questions. It can help you to pass the APICS CPIM-MPR exam, and help you to become a strong IT expert.

No comments:
Post a Comment